New Bridge at Hayle (2)
April '12
Apr (2)
Apr (3)
Apr (4)
May
May (2)
May (3)
May (4)
May (5)
May (6)
May (7)
June
Jun (2)
Jun (3)
Jun (4)
Jun (5)
July
Jul (2)
Jul (3)
August
Aug (2)
September
Sep (2)
October
Oct (2)
November
December
January '13
March
July 2012 (part 1)
Monday 2nd
South end - power and telecomm junctions
North end/new roadway - telecomm junction, etc
New roadway west wall started...
Wed 4th Jul
North end - remains of causeway and ramp. New stone wall complete.
South end, new east wall
Main road - new power junction
Main road - buried utilities
North end
North end; removing causeway ramp...
South end, new east wall
Thu 5th Jul
South end, new west wall
Main road, power cables
A digger moves from the new roadway...
..to Harbour Office road
North end - raising masonry scaffolding
Fri 6th Jul
^ New roadway^ >>masonry cladding for new wall >>
New roadway - telecomms trench, and new west wall
Raised scaffolding for stonemasons.
Main road, power cables
South end - east wall and junction box completed.
Main road power cables, west side.
Mon 9th Jul
New roadway - rebar on sheet piling
New roadway - west stone wall
Telecom junction boxes will sit flush in footpaths, either side of new roadway.