June 2012 (part 3)
Tuesday 19th
Much of causeway rubble now removed
South end traffic island. (Looks OK, but something has been missed..!)
Telecomms pipes, east side
Northern pillars
New roadway - access for utilities
East causeway, from north. NB: Bird netting piles gone.
Fri 20th Jun
North end of Causeway - scaffolding for stonemasons
Main road - preparing drains
Bridge deck given first layer of tarmac
North sluice/new roadway - preparing to infill
Thu 21st Jun
Main road - new footpath surfaced
South end/main road - telecomm access pit started
Main road - preparing drain outlet
Concreting east footpath...
South end - new west wall
New roadway...
Scaffolding for masons